UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
POWER AUTHORITY
OF THE STATE OF
PROJECT NO.2216-066
THE POWER AUTHORITY OF
THE STATE OF NEW YORK’S
ANSWER TO THE TOWN OF AMHERST’S
LATE-FILED REQUEST FOR AN ADDITIONAL STUDY
Pursuant to Section 4.32(b)(8) of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules and Regulations, 18 C.F.R. § 4.32(b)(8), the Power Authority of the State of New York (Power Authority) hereby submits its answer to the Town of Amherst’s (Amherst) late-filed additional study request. Amherst’s request is procedurally deficient, fails to demonstrate good cause sufficient to warrant additional study expenditures, and proposes a study that would no t contribute information necessary to the relicensing process. Therefore, the Power Authority respectfully requests that the Commission reject Amherst’s request.
I. BACKGROUND
On August 18, 2005,
the Power Authority filed with the Commission an Application for New License
(Application) for the Niagara Power Project (Project). Pursuant to 18 C.F.R. § 4.32(b)(6), the
Power Authority subsequently published notice of its Application in the The Buffalo News and The Niagara Gazette.1[1] As
required by the Commission’s regulations, these notices specifically stated
that “[a]ll such [additional] study requests should
be filed on or before Monday, October 17, 2005.”2 The October 17, 2005 [2]date
was established in accordance with the Commission’s regulations which, among
other things, require that additional study requests be filed with the
Commission “not later than 60 days after the application is filed . . .”[3]
On October 25,
2005, eight days out-of-time,
II. POWER AUTHORITY’S REQUEST TO REJECT
THE ADDITIONAL STUDY REQUEST
A. The
Town of
The Power Authority requests that the Commission reject Amherst’s additional study request because it: (1) is untimely; (2) fails to meet the Commission’s criteria for additional studies; and (3) offers no justification for why the request was not made during the Niagara Power Project’s ALP scoping process.
The Commission’s regulations provide clear guidance on the process for filing additional study requests. [7]Pursuant to these regulations, interested parties were required to file such requests on October 17, 2005 or sixty days after the Power Authority filed its license application. Amherst was aware of this deadline as evidenced by the fact that it submitted copies of the Power Authority’s public notice as it appeared in the The Buffalo News;[8] the town, however, filed its study request eight days out-of-time. Consisting simply of a one-paragraph letter with several miscellaneous attachments, Amherst offered no explanation for the delay and failed to demonstrate good cause for why its filing should nonetheless be considered by the Commission.
The Commission’s filing deadlines have been established to provide procedural certainty and predictability for all participants in the licensing process. At this stage of the proceeding, where the Commission’s regulations and orders will dictate the schedule for processing the Power Authority’s application (and, by extension, the implementation of the Power Authority’s settlement commitments), adherence to the Commission’s procedural regulations is necessary to ensure a timely and orderly review of the license application. By rejecting Amherst’s filing as untimely, the Commission will provide notice to all parties that future filings must conform to FERC’s deadlines in order to be considered by the Commission.
Amherst’s pleading also fails to comport with the Commission’s study request criteria. The Commission’s regulations require that:
For any such
additional study request, the requester must describe the recommended study and
the basis for the request in detail, including who should conduct and participate
in the study, its methodology and objectives, whether the recommended study
methods are generally accepted in the Scientific community, how the study and
information sought will be useful in furthering the resource goals that are
affected by the proposed facilities, and approximately how long the study will
take to complete, and must explain why the study objectives cannot be achieved
using the data already available.[9]
In this case,
Finally,
B. The Requested Study Will Not Inform
The
Commission’s Analysis of the
Assuming arguendo, that the Commission accepts
1. Background on Relevant the Power Authority
Studies
To support its license application and the development of the applicant prepared environmental assessment, the Power Authority conducted studies to determine the magnitude and geographic extent of Niagara River water level fluctuations influencing Tonawanda and Ellicott Creeks. From the data gathered from these studies, the Power Authority undertook additional resource studies to, among other things, identify Project impacts on those two creeks.
Specifically, the Power
Authority documented the extent of water level fluctuation in these two creeks
caused by all Niagara River sources (e.g., flow surges from Lake Erie,
wind, ice, and power operations) through the use of water level gages on the
Niagara River as well as Tonawanda Creek and Ellicott Creek.12[12]
These water level measurements indicated that fluctuations in Tonawanda and
Ellicott Creeks are on the order of 0.5 feet.[13] Analysis of existing stream profiles for
Together, the profiles and the field-verified presence of
hydraulic controls (i.e. riffles) confirm that the maximum extent of Tonawanda
Creek that could be influenced by median Niagara River water level is 13.7
miles upstream from the mouth and the maximum extent of Ellicott Creek is 7
miles upstream from the mouth. Based on this analysis, the area of study for
other FERC licensing studies addressing water quality, shoreline erosion,
aquatic habitat, rare, threatened and endangered species, as well as historic
and archaeological resources, was defined. [15]
2. Existing Study Data Demonstrate No Project Impacts
As part of its data
collection efforts, the Power Authority established two water quality
monitoring stations on Tonawanda Creek: one at the mouth of the Niagara River
and one located 4 miles upstream from the mouth. Three other stations were established on
Ellicott Creek, one at the mouth of Tonawanda Creek, one located one mile
upstream from the mouth, and one located 3.3 miles upstream from the
mouth. The most upstream stations on
both creeks are located in the Town of Amherst. The extensive data produced by
these stations evidence no adverse impact on water quality from Project
operations.[16]
Further, the data
suggests that the Power Authority does not have any adverse effect on the waste
assimilative capacity of either
3. No Justification for the Additional Study
As data from existing relicensing studies demonstrate, Project operations do not have an adverse impact on Tonawanda and Ellicott Creeks. Moreover, water level fluctuations associated with these creeks are caused by a number of factors; Project operations are merely a small contributory factor to the fluctuations that occur near the Town of Amherst. Accordingly, because: (1) the environmental record is sufficient for purposes of evaluating the Project and the proposed study would not contribute information necessary to the relicensing of the Project; and (2) the requested study addresses potential impacts associated with sources other than Project operations, the Commission should deny Amherst’s request for additional monitoring of Tonawanda and Ellicott Creeks.
WHEREFORE, for the
foregoing reasons, the Power Authority respectfully requests that the
Commission reject the Town of
Respectfully submitted,
David E. Blabey
Executive Vice President,
Secretary
and General Counsel
Telephone: (518) 433-6724
Facsimile: (518) 433-6781
__/s/
Jay Ryan_____________________
Jay Ryan
Van Ness Feldman, P.C.
Attorneys at Law
Seventh Floor
Telephone: (202) 298-1800
Facsimile: (202) 338-2416
Counsel to the
DATED:
November 21, 2005
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, I hereby certify that I have this day served the foregoing on each person designated on the official service list established for this proceeding.
Dated at Washington, D.C., this 21st day of November, 2005
______/s/ Jay
Ryan____________________
Jay Ryan
Van Ness Feldman, P.C.
Seventh Floor
jtr@vnf.com
202-298-1800
[1]
The Power Authority’s notice of its Application ran in The Niagara Gazette
from August 26th through August
28th 2005. The notice also ran
in The Buffalo News on August 28 and August 29, 2005.
[2] See Power Authority’s Proof of Newspaper Notice, Project No. 2216-066 (filed with the Commission on September 14, 2005).
[3] 18 C.F.R. § 4.32(b)(7).
[4] See e.g., Memo
of Paul M. Bowers (undated), submitted as an attachment to
[5]
[6] The Power Authority filed an Offer of Settlement filed with the Commission on August 19, 2005. The Offer of Settlement included a “Relicensing Settlement Agreement Addressing New License Terms and Conditions” which was executed by DEC and a number of other regulatory agencies and environmental organizations
[7] 18 C.F.R. § 4.32(b)(7)
[8] As part of the attachments submitted to the Commission,
[9] 18 C.F.R. § 4.32(b)(7). Under the Commission’s new Integrated License Process regulations, study requests must also, inter alia, “[d]escribe considerations of level of effort and cost, as applicable . . ..” 18 C.F.R. § 5.9(b)(7).
[10] Letter from Paul E. Bowers to State Senator Mary Lou Rath submitted as an attachment to
[11] E-mail from J. Molnar (
[12] These studies are summarized in the PDEA and topic
specific study reports were submitted as part of the project record at FERC. See URS Corporation, Gomez and Sullivan Engineers, P.C., and
E/PRO Engineering & Environmental Consulting, LLC. 2005. Niagara
River Water level and Flow Fluctuation Study, prep. for
the
[13] The median water level fluctuation in
the Niagara River at the mouth of
0.55 feet during the tourist season and 0.43 feet during the non-tourist season.
[14] Existing stream profiles were taken from Flood Insurance Studies.
[15] These studies are summarized in the PDEA and topic
specific study reports were submitted as part of the project record at
FERC. See Gomez and Sullivan
Engineers, P.C. and E/PRO Engineering & Environmental Consulting, LLC.
2005. Mapping of Aquatic and Riparian Habitats of Ellicott and Tonawanda
Creeks, and Tributaries to Tonawanda Creek, Prep. for
the
[16] For example, on Tonawanda Creek dissolved oxygen
concentrations varied between 6.9 and 11 mg/l, meeting NYS water quality
standards for this reach. For Ellicott Creek dissolved oxygen met NYS water
quality standards under dry weather conditions. For wet weather conditions,
dissolved oxygen fell below the NYS instantaneous standard of 5 mg/l (once at
the station at the mouth and once at the station one mile upstream of the
mouth). In addition to dissolved oxygen concentration, the Power Authority
monitored turbidity in both creeks. In general, the turbidity in Tonawanda
Creek was almost always lower at the station near the mouth than the one 4
miles upstream, regardless of the weather. This is consistent with turbidity
measurements at the NYSDEC station 20 miles upstream of the mouth
which are higher and indicative that upstream land use may be
contributing sediment and pollutants to the stream. Like Tonawanda Creek, turbidity measurements
at the mouth are less than those upstream, the result of mixing with less
turbid
[17] Waste assimilation models are used to determine the
effect of parameters such as biochemical oxygen demand, total suspended solids
and phosphorus on the quality of a stream and the resulting reduction in
loadings a discharger (Town of
[18] The
[19] This level of fluctuation is readily quantifiable by
the Town of
[20] From a velocity perspective, the