Slide 1. Title Slide

Great Gorge Railway Trail and Schoellkopf Overlook Enhancement Projects

Public Information Meeting

February 4, 2010

Slide 2.

Agenda

·       Introduction

·       Overview of the Schoellkopf Overlook Enhancements

·       Overview of the Great Gorge Railway Trail Improvements

·        ArtPark Stairways Refurbishment

·       Schedule

·       Comments 

Slide 3.

LOCATION OF PROJECTS

·       Schoellkopf Overlook

·       Whirlpool Bridges Overlooks and Trail Access

·       Great Gorge Railway Trail

Image

Slide 4

GREAT GORGE RAILWAY TRAIL

Phase I – Completed in 2004

Image

Slide 5.

GREAT GORGE RAILWAY TRAIL

Rock Scaling Efforts

Image

Slide 6.

Schoellkopf Overlook Current Condition

Image

Slide 7.

Schoellkopf Overlook Enhancements

Image

Slide 8.

Whirlpool Bridges Overlooks and Trail Access

Image

Slide 9.

Whirlpool Bridges Overlooks and Trail Access Improvements

Image

Slide 10.

Whirlpool Bridges Overlooks (Upper Level)

Image

Slide 11.

Whirlpool Bridges Overlooks (Lower Level)

Image

Slide 12.

Earl W. Brydges ArtPark Stairways Refurbishment

Image

Slide 13.

Earl W. Brydges ArtPark Stairways Refurbishment

Image

Slide 14.

River’s Edge Trail - Stairway 1

Image

Slide 14.

River’s Edge Trail - Stairway 1

Image

Slide 15.

River’s Edge Trail - Stairway 2

Image

Slide 16.

Metal Stairway Reconstruction

Image

Slide 17.

Schoellkopf and Whirlpool Bridges Overlooks Schedule

·       Stakeholders Consultation – February 2010

·       50% Design – 3rd Quarter 2010

·       90% Design – 4th Quarter 2010

·       Design Complete – 1st Quarter 2011

·       Construction – Start 2nd Quarter 2011

Slide 18.

ArtPark Stairways Refurbishment Schedule

·       Stakeholders Consultation – February 2010

·       50% Design – 4st Quarter 2010

·       90% Design – 1st Quarter 2011

·       Design Complete – 2nd Quarter 2011

·       Construction – Start 3rd Quarter 2011

Slide 19.

Comments