Rehabilitation Design for Reservoir State Park

 (May 2010)

Slide 1.

            Rehabilitation Design for Reservoir State Park

·         Public Information Meeting 2 

·         May 2010

·         Image

Slide 2.

Agenda

·         Introduction

·         Reservoir State Park Improvements – Response to Stakeholder Imput

·         Schedule

·         Comments

Slide 3.

Figure: Reservoir State Park – Site Development Plan

Slide 4.

Planned Improvements – North Field

·         Zoomed in Image of North Field with labels of the following areas (clockwise direction)

1.      Interpretive Sign and Benches

2.      Repave the exiting path to the top of the Lewiston Reservoir Sledding Hill

3.      Replace and Expand Parking Lot

4.      Winter Pavilion and Comfort Station

5.      Lighted Ice Skating Rink (Seasonal)

6.      Soccer Field Improvements

7.      Entrance Sign

8.      Reservoir Parking

9.      Memorial Site Improvements

·         Image Winter Pavilion -view from Soccer Fields

Slide 5.

Planned Improvements – South Field

·         Zoomed in Image of South Field with labels of the following areas (clockwise direction)

1.      Stormwater Treatment

2.      Expand Parking Area

3.      Comfort Station

4.      Lighted Softball Field

5.      Pavilion

6.      Field Pedestrian Loop

7.      Rehabilitate the Softball Field

8.      Pedestrian Path

9.      Model Airplane Flying Field

10.  Golf Practice Range

Slide 6.

Planned Improvements – Ball Courts and Playground Area

·         Zoomed in Image of Ball Courts and Playground areas with labels of the following areas (clockwise direction)

1.      Pedestrian Path

2.      Comfort Station

3.      New Playground Equipment and Handicap Accessible Swing

4.      Playground and Small Gazebo

5.      Rehab Existing Courts

6.      Pavilion

7.      Picnic Pavilion

8.      Install New Basketball Courts

9.      Parking Lot

10.  Rehabilitation of Maintenance Access Road

11.  Overflow Parking Area

12.  Entrance Sign

Slide 7.

Schedule

·         Public Meeting #1 – October 2009

·         90% Design – March 2010

·         Public Meeting #2 – May 2010

·         Design Complete – June 2010

·         Construction – October 2010 -2011

Slide 8.

http://niagara.nypa.gov

·         Image of NYPA website